Double Storey Extensions: The Two Rules That Decide Yours

A rear extension of more than one storey has to pass a 3 metre depth test and a 7 metre boundary test — and in a conservation area it passes neither.

By Vladimir Castravet·
Rear elevation worked over two levels — extension below, dormer and loft glazing above, Fieldway Crescent, Norbury SW16

From our Fieldway Crescent project — Norbury, SW16

A rear extension of more than one storey is permitted development only if it passes two tests, not one: no more than 3 metres beyond the rear wall of the original house, and no closer than 7 metres to the boundary opposite that wall. Both, or neither. And on article 2(3) land — which includes every conservation area — Class A permits no rear extension of more than one storey at all. Planning decides whether you may build it. The foundation trench decides what it costs.

A single-storey rear extension pushes the ground floor into the garden and stops. A double storey carries the same footprint up to first-floor level, so what would have been a flat roof becomes a room. That is the point of it: a single-storey extension gives you a better kitchen, but it does not change how many people can sleep in the house.

It is also why the planning route is harder. A two-storey mass at the back of a terrace casts a longer shadow than a single storey, and that is the objection neighbours raise first.

The 3 metre and 7 metre rules that decide your planning route

Permitted development for house extensions sits in Class A, Schedule 2, Part 1 of the Town and Country Planning (General Permitted Development) (England) Order 2015. A single-storey rear extension faces one depth test. An extension of more than one storey faces two, and has to pass both.

Class A permitted development — the tests a two-storey rear extension has to pass
WhatThe requirementSource
Depth beyond the original rear wallThe enlarged part must not extend beyond the rear wall of the ORIGINAL dwellinghouse by more than 3 metres. The deeper 6 and 8 metre allowances people quote are written for a single storey and do nothing here.GPDO 2015, Sch.2 Pt.1, Class A.1(h)(i)
Distance to the rear boundaryThe enlarged part must not be within 7 metres of any boundary of the curtilage of the dwellinghouse which is OPPOSITE the rear wall of that dwellinghouse.GPDO 2015, Sch.2 Pt.1, Class A.1(h)(ii)
Height, overall and at the eavesThe enlarged part must not exceed the height of the highest part of the roof of the existing house, and its eaves must not exceed the height of the existing eaves.GPDO 2015, Sch.2 Pt.1, Class A.1(c) and A.1(d)
Eaves near a boundaryWithin 2 metres of the boundary of the curtilage, the eaves of the enlarged part must not exceed 3 metres.GPDO 2015, Sch.2 Pt.1, Class A.1(i)
Side extensionsAn extension beyond a wall forming a side elevation of the original house may not have more than a single storey at all — nor exceed 4 metres in height, nor be wider than half the width of the original house.GPDO 2015, Sch.2 Pt.1, Class A.1(j)
Conservation areas and similarOn article 2(3) land, Class A permits NO enlargement of more than a single storey extending beyond the rear wall, and none beyond a side elevation.GPDO 2015, Sch.2 Pt.1, Class A.2(b) and A.2(c)
Roof pitchWhere the enlarged part has more than a single storey, its roof pitch must, so far as practicable, be the same as the roof pitch of the original dwellinghouse.GPDO 2015, Sch.2 Pt.1, Class A.3(c)
Side-elevation windowsAny upper-floor window in a wall or roof slope forming a side elevation must be obscure-glazed, and non-opening unless the openable parts are more than 1.7 metres above the floor of the room.GPDO 2015, Sch.2 Pt.1, Class A.3(b)
What a previous owner already spentAny TOTAL enlargement — the new part together with an existing enlargement it will be joined to — is measured against the same limits. A rear addition built by someone else may have consumed the allowance.GPDO 2015, Sch.2 Pt.1, Class A.1(ja)

Approved Documents are statutory guidance to the Building Regulations 2010 for England. Compliance is judged against the Requirements in Schedule 1; the Approved Document shows one way of meeting them. Your building control body has the final word on your specific building.

The two clauses that end it for most London houses

First, the 7 metre boundary rule. A 12 metre garden leaves 9 metres clear after a 3 metre extension, which passes. An 8 metre garden — ordinary in Fulham, Hackney and Tooting — leaves 5, and Class A is gone whatever depth you choose. Nothing in the design fixes it, because the test is measured from the boundary rather than from the house.

Second, article 2(3) land, on which paragraph A.2 permits no rear extension of more than one storey at all. Large parts of Hammersmith and Fulham, Wandsworth, Kensington and Chelsea, Camden and Islington sit inside a conservation area. There it is a full planning application from day one, and the programme has to carry a determination period.

Measure this before you pay for a drawing

Mark where the new rear wall would sit and measure to the boundary opposite. If it is under 7 metres, Class A is unavailable and you are making a planning application — a fact worth knowing before a designer starts, not after.

Where a scheme does sit inside Class A, apply for a Lawful Development Certificate anyway. A buyer's solicitor will ask for it years later, when the evidence is much harder to assemble. Our post on permitted development rules for London extensions covers what that application contains.

Foundations — where a double storey parts company with a single storey

A second storey roughly doubles the load arriving at the foundation. The trench does not double in depth, but depth stops being governed by frost and starts being governed by how the ground behaves — and in London the ground is clay.

Minimum depth and thickness for a strip foundation
WhatThe requirementSource
General minimum, to avoid frost actionStrip foundations should have a minimum depth of 0.45 m to their underside, except where founded on rock. Increase in areas of long frost or to reach satisfactory ground.Approved Document A, §2E4
On shrinkable clayOn clay with a Modified Plasticity Index of 10% or more: not less than 0.75 m on low shrinkage, 0.9 m on medium shrinkage, 1.0 m on high shrinkage. Increase where trees are nearby.Approved Document A, §2E4
Width and thickness of the concreteThe foundation should project each side of the wall by at least the depth of the foundation below the wall face; the thickness must be not less than that projection, and never less than 150 mm.Approved Document A, §2E2–2E3
Bearing for the steel and lintels aboveBearing length 150 mm or greater, reducing to 100 mm only where the clear span is 1200 mm or less.Approved Document A, §2C24(a)

Approved Documents are statutory guidance to the Building Regulations 2010 for England. Compliance is judged against the Requirements in Schedule 1; the Approved Document shows one way of meeting them. Your building control body has the final word on your specific building.

Two qualifications sit inside that clay clause and both cost money. Shrinkable clay means a Modified Plasticity Index of 10% or more. And those depths are floors, not answers — the same clause says to increase them to transfer the loading onto satisfactory ground, or where there are trees nearby.

Trees move the number here more than anything else. A mature tree within influencing distance of a clay foundation drives the trench well past 1.0 m, and it need not be your tree. One removed a few years ago is worse than one still standing, because the clay is still recovering. The mechanics are in foundation depth and why it changes on site.

Why the party wall count changes too

A deeper trench brings a second section of the Party Wall etc. Act 1996 into play. Raising the shared wall is work to a party structure and needs a notice at least two months ahead under sections 2 and 3. Section 6 covers excavation separately: within 3 metres of a neighbouring structure and below the level of its foundations, or within 6 metres and cutting a 45° line beneath them, on at least one month's notice.

A single-storey extension on shallow footings often engages only the first. A double storey founded on a metre of clay engages both, on both sides of a terrace. What that changes is not only cost but sequence — the notices are served at different times and run different clocks.

What the building regulations require once planning is settled

Planning decides whether you may build it. Building regulations decide what it has to be.

The clauses a two-storey rear extension is judged against
WhatThe requirementSource
New fabricMaximum U-value: walls 0.18, ground floor 0.18, roof 0.15 W/(m²·K).Approved Document L Volume 1, Table 4.2
Windows and glazed doorsWindows: maximum 1.4 W/(m²·K) or Window Energy Rating Band B. Doors more than 60% glazed: 1.4 or Doorset Band C. Rooflights: 2.2 on developed surface area.Approved Document L Volume 1, Table 4.2
Escape from the new first-floor roomOn a house whose upper storeys are a maximum of 4.5 m above ground, escape is via windows or doors from habitable rooms — no protected stairway required.Approved Document B Volume 1, §2.2–2.3
The escape window itselfOpenable area at least 0.33 m², at least 450 mm high and 450 mm wide, with the bottom of the openable area not more than 1100 mm above the floor.Approved Document B Volume 1, §2.10
If any storey ends up more than 4.5 m above groundProvide a protected stairway or an alternative escape route. Fire-resisting construction minimum REI 30, fire doorsets minimum E 30.Approved Document B Volume 1, §2.5–2.6
A new or altered private stairMaximum rise 220 mm, minimum going 220 mm, maximum pitch 42°. Twice the rise plus the going should fall between 550 mm and 700 mm.Approved Document K, Table 1.1
Headroom over that stairMinimum 2 m on the access between levels, measured from the pitch line.Approved Document K, §1.11, Diagram 1.3

Approved Documents are statutory guidance to the Building Regulations 2010 for England. Compliance is judged against the Requirements in Schedule 1; the Approved Document shows one way of meeting them. Your building control body has the final word on your specific building.

What changes on fire when you add a floor

Adding a storey at the back of a two-storey house normally keeps every floor within 4.5 m of ground, so the new bedroom needs an escape window meeting paragraph 2.10 and nothing more.

The trap is a house that is already three storeys. Cross 4.5 m on any storey and a protected stairway is required through the whole house — a whole-house cost triggered by a rear extension. That belongs in the feasibility conversation, not in a variation six weeks into the build. We have written about what actually sits inside two quotes for the same job, and this is the classic line one of them has left out.

The five things that move the price

There is no double storey rate on this page. 2VP has delivered single-storey rear extensions and side returns rather than double storeys, so any figure here would be typed rather than billed. For your own house, the estimator prices it line by line from the same model we price real work with. What is worth understanding is how the price is built, because a double storey is not two single storeys stacked.

Foundation depth. Found in a trial hole, not on a drawing. Clay class, trees and the depth of the existing footing all push it down, and depth is bought by the metre. This is the line most likely to differ between two quotes.
How the roof resolves. Tying a new pitched roof into the existing one — at a pitch Class A requires to match — is a different job from a flat roof over a single storey. The junction is also where water gets in.
The first-floor span. With an open-plan ground floor the new floor crosses with no wall beneath it. The longer the span, the heavier the steel, and the more of it has to be lifted into a back garden.
Services upstairs. A new bathroom needs soil, water and heating capacity. A boiler already at its limit becomes a boiler replacement, which is a line people meet late.
Whether the stair is touched. Reaching the new room off the existing landing is cheap. Altering the stair is not — it is the hardest thing to move in a terrace, and it takes rooms with it.

Sitting outside any build figure: the architect and the structural engineer, the party wall surveyor on each affected side, and the determination period, which is not a cost until you are renting somewhere else. Party wall fees have their own range and their own logic, set out in what a party wall agreement costs.

The one place a double storey genuinely saves money

Per square metre it should be cheaper than a single storey. The foundation, the ground works, the drain connection and the scaffold are bought once and carry two floors, so the rate falls even as the total rises.

That saving is conditional. It holds only if both floors are built as one project. Adding the upper floor in three years means stripping a roof you have paid for and re-erecting scaffolding around a finished house. If you want the upper floor at all, it is materially cheaper built now.

When a double storey extension is the wrong answer

Two of these are absolute and the rest are judgement.

The garden is under about 11 metres. Three metres of extension plus seven metres of clearance is ten before anything else, and gardens are not measured to the millimetre. Below that you are asking an officer to accept a two-storey mass on a short garden.
You are on article 2(3) land and want certainty. Class A gives you nothing here, so the whole scheme rests on a planning judgement. That is not a reason never to apply — it is a reason not to plan a programme around a certificate you cannot get.
You only need a better kitchen. The upper floor is most of the extra cost and all of the extra planning risk. For a brighter ground floor, a single-storey rear or a side return does it for less — see the side return guide.
The loft is still empty. Per square metre a loft conversion is usually the cheaper bedroom, and it takes no garden at all. Worth comparing before the garden is spent.
The house has a bigger problem. New rooms beneath a failing roof or above untreated movement give you good space in a bad building. If cracking is the concern, start there instead.

The comparisons above have their own posts: which loft conversion type suits your house, the side return extension guide, and underpinning explained for London homeowners if movement is what is really on your mind.

Our interest, declared

2VP builds extensions, and we own AtoZ Design & Glass, which supplies and installs the glazing. A double storey is a larger contract carrying more glazing, so we profit directly from the bigger option. Read our comfort with two floors in that light — and make us price the single storey alongside it, same drawing, same finish, same day.

Eight checks before you commission a drawing

  1. 01Measure to the rear boundary. Mark where the new rear wall would sit and measure to the boundary opposite it. Under 7 metres and Class A is gone, whatever the depth.
  2. 02Check whether you are on article 2(3) land. Your council's map answers it in a minute. In a conservation area, no rear extension of more than one storey is permitted development at all.
  3. 03Establish where the ORIGINAL rear wall was. The 3 metre limit runs from the original dwellinghouse, and paragraph A.1(ja) measures any total enlargement against the same limits. A previous owner may have spent the allowance.
  4. 04Dig a trial hole against the existing rear wall. Before anyone prices the groundwork. It shows the footing you are tying into and the ground you are founding on — the two things that move the number most.
  5. 05Map every tree within influencing distance. Yours, the neighbours', and any removed in recent years. On clay these drive the trench past the Approved Document A minimums, and a removed tree is worse than a standing one.
  6. 06Count the party wall notices, on both sides. Raising the shared wall engages sections 2 and 3 at two months. Excavating below the neighbour's footings engages section 6 at one month. On a mid-terrace, assume both, twice.
  7. 07Check the escape route against 4.5 metres. Every storey within 4.5 m of ground and an escape window will do. Above it, price a protected stairway through the whole house before you commit.
  8. 08Price the single storey alongside it. Same drawing, same finish, same day. The upper floor should have to justify its cost in writing, against the alternative, before you sign for it.

The one line to take away

Measure the 7 metres to the rear boundary first. On a typical London garden that single dimension decides whether this is a certificate or a planning application — and it costs nothing to establish, unlike everything that follows it.

2VP is the builder, not a marketplace: one contract, one named project lead, and no introducer fee stacked on the build cost. On a job where the foundation depth is found rather than designed, the question of who is accountable when the ground disagrees with the drawing is not an abstract one.

You pay weekly, against work already done10% to mobilise, then weekly against work already done — with 5% held past handover: 2.5% released at practical completion and 2.5% at the end of the 12-month defects period. Your money never gets ahead of the build.
Every variation priced and dated firstNothing is spent on a change until you have approved it in writing, with its cost and its effect on the date.
The measured survey is credited in fullIf you appoint us, the pre-contract survey fee comes off your contract rather than sitting on top of it.
A completion date, in the contractNot an estimate. It is written in, and only a variation you approve can move it.
Common questions

Straight answers

The 2VP Certainty Package

The home you actually want, finished on the date in the contract — and you watch every day of it happen from your phone.

Your number in 60 secondsItemised stage breakdown in 2 minutesSurvey within 7 days

You answer 3 questions. We do the drawings, planning, party wall, trades and snagging.

Before anything is signed
Full measured survey + 3D design visualisation
You see the finished room before you commit to building it
£1,500
RIBA architect design by Nick Elias
Concept, planning and technical drawings by one named architect
£8,000–£15,000
Completion date written into the contract
A date you can plan a life around, not 'TBC at build start'
Included
While we build
No variation without your written approval
Nothing is added to your bill that you did not sign for first
Included
Friday video walkthrough of your site, every week
You know what happened this week without driving over
£1,200/yr
One named project lead, one channel, 24-hour response
You never chase a company — you message a person
Included
Daily photo diary + client dashboard
Everything photographed before it is covered up
Included
Fixtures at our trade pricing, passed through at cost
Our discount is yours, not a margin we keep quiet about
10–20% on materials
After we hand over
6-month snagging visit
We come back once the house has moved and settled
£750
12-month workmanship warranty on second-fix fittings, signed by the trades
The people who built it are on the hook for it, by name
Included
Annual check-ins for 2 years
We come back. Every year. No charge.
Included
Our guarantee
We finish on the agreed date, or we pay you £500 for every week we are late.
The date is in the contract, and so is this. Only a variation you approve can move it.
What you are not risking
  • 10% to mobilise, then weekly against work already done — with 5% held past handover: 2.5% released at practical completion and 2.5% at the end of the 12-month defects period
  • £550 survey fee credited in full against your contract
  • Every variation priced and signed before a penny is spent
4.8★ from 16 Google reviews — including the 1-star, published in full.
Get my price in 60 seconds

No email needed to see your range. Quotes hold for 21 days, then materials re-price.

We are not the cheapest. If price is the only factor, we may not be the right fit — and that is fine.

Get my price in 60 secondsExtensionsExtension costs by areaBuilders in your areaAll cost guides
If this is your project

The home you actually want, finished on the date in the contract — and you watch every day of it happen from your phone.

How fast
  • Your number in 60 seconds
  • Itemised stage breakdown in 2 minutes
  • Survey within 7 days
What you do

You answer 3 questions. We do the drawings, planning, party wall, trades and snagging.

What protects you
  • 10% to mobilise, then weekly against work already done — with 5% held past handover: 2.5% released at practical completion and 2.5% at the end of the 12-month defects period
  • £550 survey fee credited in full against your contract
  • Every variation priced and signed before a penny is spent

The date is a term of the contract. We finish on the agreed date, or we pay you £500 for every week we are late.

Do not take our word for it

4.8 from 16 Google reviews

Every review is published in full on our reviews page, including the one-star. Google is the only platform we quote a rating for, because it is the only one we can evidence.

★★★★★
As a structural engineer, I've collaborated with 2VP Projects Ltd on several residential projects in London. Their attention to detail, proactive site management, and clear communication make every stage—from design to execution—smooth and efficient. It's rare to find a contractor who values both precision and professionalism at this level. A truly reliable partner.
Igors Smirnovs · Structural engineer we have worked with · June 2025
★★★★★
Great company to work with. Professional, reliable and easy to deal with. Vladimir and the team are always responsive, straightforward and genuinely care about doing things properly. I've had a very positive experience working with 2VP and would happily recommend them.
Sheen Delicatessen · Business client · August 2026
★★★★★
Extension went smoothly from start to finish. Communication was great throughout, and the team delivered exactly what we asked for. Thank you, 2VP!
Dan Martea · August 2026
Warranties and protections

What is covered, and by whom

A builder’s own guarantee is worth exactly as much as the company standing behind it. Here is what comes as standard, what you can add, and what has to come from somebody other than us — set out in full on our insurance and guarantee page.

Included in the contract
  • 12-month workmanship warranty on second-fix fittings
  • £5M public liability
  • £10M employer's liability
  • £2M professional indemnity
Optional, on request
  • HomePro insurance-backed guarantee, 10 years
  • Priced at 2.5% of the contract sum
  • Underwritten by an insurer, so it survives us
Not from us
  • 10-year structural warranty on a new dwelling (NHBC / LABC / Premier)
  • Professional fees — architect, engineer, building control
  • We will tell you when you need one rather than let you find out